Kaohsiung MRT Siaogang–Linyuan Line Phase 2 Successfully Awarded, Targeting Completion and Service Launch in 2034
Information Management Office
115-05-08
231

The second phase of the Kaohsiung MRT Siaogang–Linyuan Line, a key project supporting industrial development in southern Kaohsiung and the growth of Siaogang and Linyuan districts, has been successfully awarded, according to an announcement by the Kaohsiung Mass Rapid Transit Bureau today. The Phase 2 civil works contract was successfully awarded on May 7, completing the final procurement package for the entire Siaogang–Linyuan Line and marking another major step toward the target of commencing operations in 2034.

Following approval of the comprehensive planning proposal by the Executive Yuan on September 23, 2022, the Kaohsiung City Government immediately initiated design work and actively proceeded with procurement for electromechanical systems, design services, and civil construction works. The electrical and rail systems contracts were awarded in 2023. To ensure timely completion, civil construction was divided into two phases. The first phase was awarded in 2023, while the second phase—covering the section from the southbound shield tunnel near RL3 New Materials Circular Economy Industrial Park Station to RL7 Linyuan High-Value Industrial Park Station—was successfully awarded on May 7, 2026. This completes the final procurement milestone for the project.

The Siaogang–Linyuan Line is a key infrastructure project under the Executive Yuan’s Greater Southern New Silicon Valley Promotion Plan. In line with Kaohsiung’s policy of prioritizing major transportation infrastructure, the route serves three national-level industrial parks: Linhai Industrial Park, Linyuan Industrial Park, and the New Materials Circular Economy Industrial Park. The line will operate using the same system as the Kaohsiung MRT Red Line, enabling through-service operations without transfers. It will connect industrial parks in northern and southern Kaohsiung with major transportation hubs, including Kaohsiung International Airport, Taiwan High Speed Rail stations, and Taiwan Railway stations, promoting balanced regional development and serving millions of tourism and recreational trips annually. The project will also strengthen links along southern Taiwan’s semiconductor S-Corridor, including major investments by TSMC, helping drive the transformation and upgrading of the petrochemical industry toward higher-value development.

The Siaogang–Linyuan Line will extend approximately 11.59 kilometers. Beginning at the reserved tunnel connection south of Kaohsiung MRT Red Line R3 Station, the route will continue underground along Yanhai 2nd Road, Yanhai 3rd Road, Zhongmen Road, and Yanhai Road Sections 4 through 2 before terminating near the Linyuan High-Value Industrial Park. The line will include seven stations in total.

The project has currently reached 14.32% completion rate. With procurement for the entire line now finalized, full-scale construction will proceed as planned. Once completed and operational, the line is expected to encourage travelers to shift from private cars and motorcycles to public transportation, reduce traffic risks associated with mixed passenger and freight traffic, and provide safe, direct, high-quality, and convenient transit services, ushering Kaohsiung into a new era of seamless, transit-oriented mobility.